Pellet Plant Layout: Six Stages in Your Shedthe six stages in order, and the rectangle each capacity wants
A 500 kg/h wood pellet production line needs 120 m² of covered floor at 4.5 m clear height, and 5,000 kg/h needs 900 m² at 9 m. Those are the figures we quote, and they are almost never the reason a site fails — a shed of the right area in the wrong shape fails first. This is the six stages in order, the rectangle each capacity wants, the clearances that decide whether a die can come out, and the material store that is in none of those numbers.
- 120 m² at 500 kg/h, 900 m² at 5,000 kg/h
- Height is set by the dryer, not the pellet mill
- 2 m of clear floor at the die end, or no die change
- A calculator: does your shed take it
We draw the production line into your shed · 1:50, conveyor lengths set to your floor, before the foundation is poured

The short answer
A production line is a run, not a block. Six stages in a fixed order, and the room has to be long enough before it is big enough.
A wood pellet production line is six stages in a fixed order — wood chipper machine, wood hammer mill, rotary drum sawdust dryer, pellet mill, pellet cooler, pellet packing machine — and the material only ever moves forward through them. That makes the layout a run of 18 m at 500 kg/h and 45 m at 5,000 kg/h, in a room 7 m and 20 m wide, under a roof 4.5 m and 9 m clear. A shed of 120 m² at 18 × 7 m takes the 500 kg/h line. The same 120 m² at 12 × 10 m does not, because nothing in the run can be folded back on itself without a second conveyor and a second lift.
The floor, rectangle and height figures are the ones we quote on a production line, measured to the outside of the machines and the walkways between them. They exclude the raw material store, the goods, the office and the truck apron, which on most sites are as large again — the store table further down puts a number on the first of them.
What each stage asks of the building
Read the second column as a list of things the builder has to provide. Every one of them is cheaper to provide on a drawing than on a finished slab.
| Stage | What the building has to give it | The model, and its size | Height it sets |
|---|---|---|---|
| Wood chipper machine | A level apron at the head of the run, and 4 m in front of the feed opening for a truck, a trailer or a belt conveyor | DP-420B 1.6 × 0.6 m at 11 kW; DP-700B 2.45 × 1.5 m at 37 kW | 1.2–1.45 m |
| Wood hammer mill | 1 m on three sides for a screen change, and a duct out through a wall to the cyclone, which stands outside | FS-50-40B about 1.8 × 1.2 m at 22 kW; FS-50-60B at 37 kW | 2.5 m, plus the cyclone |
| Rotary drum sawdust dryer | The longest single item on the site, and the stage that most often ends up under its own roof rather than inside the shed | HG-G 1000 drum 1.0 m across, 4.3 t; HG-G 1800 1.8 m across, 23.8 t | 7–9 m to the cyclone top |
| Pellet mill | 2 m of clear floor at the die end, and a foundation block isolated from the slab so the vibration does not reach the bagging end | PM-D450B 2.6 × 0.8 m, 1.2 t; PM-D580B 2.8 × 0.8 m | 1.3–1.6 m, plus 1 m to lift a die |
| Pellet cooler | Loading from above, so a mezzanine or a bucket elevator beside it — this is the stage that decides whether the building has a second floor | LQ-70 about 1.8 × 1.2 m; NL-11 and NL-14 are the counterflow pair | NL-11 3.2 m, NL-14 3.4 m |
| Pellet packing machine | Bag stack space beside it and a clear run to the door — a pallet or a conveyor, never a person carrying 50 kg bags 20 m | DCS-Z-D-50 about 1.5 × 1.5 m at 1.1 kW | 2.6 m for the hopper |
The order of the six is fixed by the process, so the only real freedom is how far apart they stand. Every metre between two stages is a conveyor that has to be built, guarded and kept clear, which is why a tight layout is cheaper to run than a generous one — up to the point where a die cannot come out. The pellet cooler page is where the loading-from-above problem is set out in full, and the biomass sawdust dryer page is what the 7–9 m of clear height is for.
Four columns will not fit a phone. Swipe the table sideways for the model sizes, or read the first two, which are the ones the builder works from.
The stage that catches people out is the pellet cooler. It has to be loaded from above, so either the building has a mezzanine with the pellet mills underneath and the pellet cooler on top, or there is a bucket elevator standing beside it doing the same job in 3.2 m of height. On a 500 kg/h build the elevator is the cheaper answer and on a 2,000 kg/h build the mezzanine is, because at that size the structure is carrying the buffer silo anyway. Either way it is a decision taken on the layout drawing, not after the machines arrive.
The second is the wood chipper machine, which is the one stage that wants space outside the building rather than inside it. Logs and slabs arrive on a truck or a trailer, and 4 m of apron in front of the feed opening is what lets the truck tip or the trailer be unloaded without a second handling step. Put the wood chipper machine inside a shed with a 3 m door and the material gets handled twice, by hand, for the life of the site.


What each output capacity needs, as a rectangle
Area on its own does not decide it. These are the rectangles we draw on, with the clear height that goes with each — measured to the outside of the machines and the walkways between them.
| Output capacity | Covered floor | A rectangle that works | Clear height |
|---|---|---|---|
| 500 kg/h — one PM-D450B | 120 m² | 18 × 7 m | 4.5 m |
| 1,000 kg/h — two PM-D450B | 200 m² | 25 × 8 m | 6 m |
| 1,000 kg/h — one HML-560 | 220 m² | 22 × 10 m | 7 m |
| 2,000 kg/h — two HML-560 | 380 m² | 32 × 12 m | 7 m |
| 5,000 kg/h — three HML-600 | 900 m² | 45 × 20 m | 9 m |
The rectangle is the one we draw by default, not the only one. 200 m² as 25 × 8 m suits two flat die pellet mills because they sit side by side across the width; the same 200 m² as 20 × 10 m works as well, and 14 × 14 m does not, because the run needs 25 m in one direction and no amount of the other direction substitutes for it.
Four columns will not fit a phone. Swipe the table sideways for the clear height, or read the first three, which are the floor.
The two 1,000 kg/h rows are the interesting pair. Two flat die pellet mills need 200 m² at 6 m clear; one vertical ring die pellet mill needs 220 m² at 7 m. The vertical ring die pellet mill takes more floor and more height for the same output, and what it buys is a single machine to feed, a single die to change and one fewer conveyor. The multi-machine page works that trade through on downtime rather than on floor.
Nothing below 500 kg/h is in the table because nothing below 500 kg/h is a production line. A single flat die pellet mill from PM-D225B at 80 kg/h to PM-D580B at 800 kg/h stands in a shed of its own with a hammer mill, and the run is whatever the two machines need. The six-stage figures start when the dryer, the pellet cooler and the pellet packing machine are in the build, because those are the stages that make the length.

The gaps that decide whether the production line can be maintained
Every figure here is a person standing somewhere with a tool in their hand. Get one wrong and the production line still runs — it just cannot be repaired.
| Where | Clear space | What the space is for |
|---|---|---|
| Die end of a flat die pellet mill | 2 m × the width of the pellet mill | A die plate comes out whole. You stand behind it and swing a bar, and a plate on a PM-D450B needs the room to come out and be laid down without being lifted over anything |
| Around a vertical ring die pellet mill | 2.5 m on the crane side, 4 m of headroom above the die | The die and roller assembly lifts out as one unit on a hoist. HML-560 to HML-700 are all taller than a person and none of them is a two-hand lift, which is why the crane rail is in the building rather than rented for the day |
| Between two pellet mills side by side | 1.5 m | Wide enough to change a die on one while the other runs — which is the entire reason for buying two rather than one |
| In front of the pellet cooler | 1.2 m, and the mezzanine above it | The screen deck slides out at the front, and the deck is longer than the pellet cooler is deep, so the clearance has to be in front of it and not above it |
| From a wall to a motor | 0.8 m | Motor removal, belt tensioning and a grease gun. Anything pushed against a wall runs until the day it stops |
| Walkways | 0.9 m clear, 1.2 m where a bag or a pallet goes | Not a fire regulation — the width a person carrying 50 kg actually uses without turning sideways, measured at the narrowest point on the route |
| At the pellet packing machine | 3 m to the door, 4 m if a truck backs in | Bags leave on a pallet or a conveyor. Carrying them is the slowest and most expensive conveyor on the site, and it is the one most layouts end up with |
Add the 200 mm slab to all of it, and put the pellet mills on their own block. Foundations are ordinary reinforced concrete at 200 mm for everything except the pellet mill, which wants a separate block isolated from the slab so the vibration does not travel into the bagging end — we send the block dimensions with the layout drawing. Compressed air is 0.6 m³/min at 7 bar for the bag clamp and the cylinder valves, and it needs a drop at the bagging end.
Three columns will not fit a phone. Swipe sideways for the reason column, which is the part that decides the number.
The clearance people cut first is the die end, because it looks like wasted floor. It is the one that costs the most to get wrong: a flat die pellet mill whose die cannot be drawn straight out gets its die changed with a crowbar and two people, which turns a 20-minute job into half a shift, and a half shift on a 500 kg/h line is 4 t of pellets. The flat die pellet mill page has the die change sequence machine by machine.
The clearance people cut second is the walkway, and it is cut to 0.6 m because 0.9 m looks generous on a drawing. A person carrying a 50 kg bag needs about 0.9 m and does not walk in a straight line, so 0.6 m becomes a route that goes round the long way, and the long way is where the pallet gets left. Draw the walkway at 1.2 m and the floor will be used the way the drawing says.
The building nobody puts in the floor plan
Every figure above is the production line. The material it eats is in none of them, and at 500 kg/h it is a quarter of the floor again.
| Output capacity | Pellets a day, 16 h | Sawdust in at 20 % | Store it needs |
|---|---|---|---|
| 500 kg/h | 8 t | 9.2 t | 46 m³ — a 6 × 6 m bay at 1.3 m deep |
| 1,000 kg/h | 16 t | 18.4 t | 92 m³ — an 8 × 8 m bay at 1.5 m deep |
| 2,000 kg/h | 32 t | 36.8 t | 184 m³ — a 12 × 12 m bay at 1.3 m deep |
| 5,000 kg/h | 80 t | 92 t | 460 m³ — a 16 × 20 m bay at 1.5 m deep |
Sawdust at 200 kg/m³ loose, 20 % moisture in against 8 % out, which is 1.15 t of material for every t of pellets. A bay filled 1.5 m deep holds about 300 kg per m² of floor, so the 5,000 kg/h store is 307 m² — a third of the 900 m² the production line itself needs — and it has to be under a roof, or the water you paid a dryer to remove comes straight back. The moisture page is where the 1.15 comes from.
Four columns will not fit a phone. Swipe sideways for the store size, which is the figure this table exists for.
The store is the figure that changes a site plan, because it is the one nobody budgets for. A buyer with a 120 m² shed and a 500 kg/h line has 120 m² of line and 31 m² of sawdust bay at 1.5 m deep, plus the bagged output waiting for a truck — and the three together are what the roof has to cover. Put the bay outside and open and the material arrives at the dryer wetter than the figure the dryer was sized on.
Finished goods are the smaller half and the one that gets forgotten. A day of output at 500 kg/h is 8 t of pellets, which bagged is about 12 m³ — a pallet stack two deep against a wall, or a truck that comes every day. If the truck comes weekly the same output is 84 m³, and that is a second building. Ask what the haulage actually is before the floor is poured, because it decides more of the layout than the pellet mill does.
Does your shed take the production line?
Four numbers from the building you already have. The answer is the first thing that fails, and on most sheds it is not the area.
It fits. 126 m² against the 120 m² a 500 kg/h line needs, 18 m of run against 18 m, and 4.5 m of clear height against 4.5 m.
The bands are the rectangles we quote on: 120 m² at 500 kg/h, 200 m² at 1,000 kg/h with two flat die pellet mills, 380 m² at 2,000 kg/h and 900 m² at 5,000 kg/h. A capacity between two bands is checked against the larger one, because pellet mills come in models and not in percentages. Material is worked out at 16 hours a day, 20 % moisture in against 8 % out, and sawdust at 200 kg/m³ loose.
The order the checks run in is deliberate. The run comes first because it is the one thing you cannot buy your way out of — a shed that is 4 m short needs a second conveyor, a second lift and a transfer point that blocks. The clear height comes second because raising a roof is a structural job. Area comes last because area is the one figure that is usually already there.
Try the shed that fails this most often: 120 m² as 12 × 10 m for a 500 kg/h line. The area passes — 120 m² against 120 m² — and the run does not, because the production line wants 18 m and the room has 12. That is not a smaller production line, it is a different layout: an L with the dryer across the end, one extra conveyor and about 6 kW more installed. The sizing page is what to do if the capacity has to come down instead.
Measuring the shed before you measure the capacity
Four numbers, taken with a tape rather than from a drawing. Every one of them is cheaper to find now.
Measure the longest clear run, not the floor
A 120 m² shed is 18 × 7 m or 12 × 10 m, and only one of those takes a 500 kg/h line. Write down the longest unobstructed line you can draw from wall to wall, then the width at right angles to it.
Take the height under the lowest obstruction
Not the eaves. The truss, the crane rail, the light fitting, the duct that is already there. 4.5 m at 500 kg/h and 9 m at 5,000 kg/h, and it is the dryer cyclone that needs it.
Draw the die end before anything else
2 m of clear floor at the head of every flat die pellet mill, and 2.5 m plus a hoist over every vertical ring die. If those two do not fit, the layout is wrong before it is drawn.
Add the store, the bags and the truck
46 m³ of sawdust at 500 kg/h and 12 m³ of bagged pellets a day, neither of them in the 120 m², both of them on the same site and under the same roof if the material is coming in wet.
The measurement that decides the most is the one people take last, which is the clear run. Floor area is on the deeds and the run is not, so a buyer arrives with 120 m² and no idea whether it is 18 m long or 12. Take a tape to the shed before the quotation, not after — the difference between those two shapes is a conveyor, a lift and a transfer point, and none of the three is on the equipment price.
The second thing to measure is what is already overhead. An existing shed usually has a truss at 4 m, a light fitting at 3.8 m and a duct from whatever the last tenant did. The clear height is the distance from the floor to the lowest of those, and it is the number the dryer has to fit under. If it does not, the dryer goes outside under its own roof, which is cheaper than raising a building and is what most sites end up doing.
Three ways to put six stages into a room
The order of the stages is fixed. The shape of the room is not, so the layout question is really which of these three you can build.
-
One straight run
The default, and the one the six-stage order wants. Material enters at one end and leaves at the other, every conveyor is short, every machine is reachable from both sides and nothing has to be lifted twice. It needs the full length — 18 m at 500 kg/h, 45 m at 5,000 kg/h — so it wants a shed that is long and narrow rather than square. Cheapest to run, hardest room to find.
-
An L, with the dryer across the end
What you build when the shed is wider than it is long. The dryer and its cyclone sit across the bottom of the L and the run turns 90° after it. It works, and it costs one extra conveyor, one extra lift and one transfer point that will block at some moisture content — about 6 kW more installed on a 500 kg/h build. Put the turn after the dryer and not before it, so the wet material has the shortest possible path.
-
Two levels, with the mills under a silo
What a 2,000 kg/h build wants: the dryer and the buffer silo above, the pellet mills and the pellet cooler below, and gravity doing the conveying that the other two layouts do with belts. It is the cheapest layout per t and the one that needs 7–9 m of clear height plus a structural engineer, so it is a building decision rather than an equipment decision — and it is why the height figure in table above is not negotiable at that size.
The three are not equally available. A straight run is the cheapest to run and the hardest room to find, an L costs one conveyor and one transfer point, and two levels cost a structure and save a conveyor every time the material moves. What none of them can do is fold the run back on itself more than once — a shed with the right area in the wrong shape does not need a smaller line, it needs a different layout, and that conversation belongs on the drawing.
What buyers ask about fitting a production line into a shed
Eight questions, answered the way we answer them on the phone.
How much floor space does a pellet plant need?
120 m² of covered floor at 500 kg/h, 200 m² at 1,000 kg/h with two flat die pellet mills, 380 m² at 2,000 kg/h and 900 m² at 5,000 kg/h. Those figures are the production line only — they exclude the material store, the bagged output and the truck apron, which together are usually as large again.
How high does the building have to be?
4.5 m clear at 500 kg/h, 6 m at 1,000 kg/h, 7 m at 2,000 kg/h and 9 m at 5,000 kg/h, measured under the truss or the crane rail rather than to the eaves. The height is set by the rotary drum sawdust dryer and its cyclone, and then by the buffer silo over the pellet mills — never by the pellet mill itself, which is 1.3–1.6 m tall.
Can a production line go in a shed that is wider than it is long?
Yes, as an L: the run turns 90° after the dryer, which costs one extra conveyor, one lift and one transfer point. What it cannot do is fold back twice. A 120 m² shed at 12 × 10 m will not take a 500 kg/h line that needs an 18 m run, and the answer there is a different layout rather than a smaller line.
Does the pellet mill need a special foundation?
A separate reinforced concrete block, isolated from the slab so the vibration does not travel into the bagging end. Everything else in the six stages sits on 200 mm of ordinary reinforced concrete. We send the block dimensions with the layout drawing, and the block is poured before the machines arrive rather than after.
How much clear space is needed around a pellet mill?
2 m at the die end of a flat die pellet mill, because a die plate comes out whole and you stand behind it to swing a bar. Around a vertical ring die pellet mill, 2.5 m on the crane side and 4 m of headroom, because the die and roller assembly lifts out as one unit on a hoist.
Where does the raw material go?
In a covered bay, and it is not in the floor area above. At 500 kg/h over 16 hours the production line eats 9.2 t of sawdust at 20 % moisture, which is 46 m³ at 200 kg/m³ — a 6 × 6 m bay at 1.3 m deep. At 5,000 kg/h it is 460 m³, which is 307 m² of floor and a third of the area the production line itself needs.
Can the dryer stand outside?
Often it has to, and it is the one stage that usually does. The drum, the furnace and the cyclone are the tallest and longest items on the site, and a separate roof over them is cheaper than raising the whole building by 2 m. Keep the feed and discharge conveyors under cover, because that is where the material loses and gains moisture.
Do I need a layout drawing before I order?
Before you pour concrete, yes. We draw at 1:50 to your shed, with the conveyor lengths between the stages set to your floor, and that drawing is what the foundation contractor works from. Send the shed dimensions and the door positions and we will draw yours before the order rather than after the crate arrives.
Send the shed dimensions and we will draw the production line into it
Length, width, clear height and where the doors are. We come back with the six stages set out at 1:50, the conveyor lengths between them, the foundation blocks and the floor area the store and the bags take outside the production line — before anything is poured.
What happens after you send it
We reply with a layout drawing at 1:50 to your shed, the six stages in order with the conveyor lengths between them, the foundation block sized for the pellet mills, the clear height each stage needs and the floor the store and the bagged output take outside the production line. If the shed will not take the capacity you want, we say so and quote the capacity it will take.